Projectplan & status

Horos - Solarglider

News:

2017-03-14

Due to other projects (Build of MC-30 and job) the sotar glider is on hold at the moment. If you interested in more details please send me an email

2016-12-17: X-plane - Simulation is performing well

2016-12-12: Model for X-plane to verify flight performance

2016-10-09: Human dummy in real size to design an optimal cockpit

2016-10-09: Human dummy in real size to design an optimal cockpit

2016-10-04: Rough wing design done

2016-10-02: Aileron, Rudder and power unit 1st design finished

2016-09-29: Motor, Gearbox and Propellershaft design done to build up the test bench

2016-09-29: Motor, Gearbox and Propellershaft design done to build up the test bench

Rough preliminary milestones of development:

This overview shows a rough planning of the complete development and building of the Horos solar motorglider.

Based on success, support but also problems during the project schedule will be updated.

Aerodynamic design and simulation using „xflr5“

1st design finished

2016/08

Bench test of power unit

open

2016/10-11

Solarpanel (mechanical design, definition of production)

open

2016/11-12

FEM analysis and definition of wing spars

open

2016/11-12

Construction of details

open

2017/01-03

Build of mould for fuselage

open

2017/04-06

Build of fuselage + beam

open

2017/07-08

Build aileron and rudder

open

2017/09

Build of wing and solar panels

open

2017/10-12

Integration of mechanical control equipment

open

2018/01-03

Integration of electric components

open

2018/04-05

1st flight

open

2018/06